Oyu Tolgoi review raises doubts over Rio Tinto stance on cost overruns

(Reuters) -Turquoise Hill Resources said an independent review of$1.4 billion in cost overruns at the Oyu Tolgoi mine in Mongolia suggested that the project's troubles were not caused by the geology issues that mine operator Rio Tinto blamed https://www.reuters.com/article/us-rio-tinto-output-idUKKCN1UA2HH in 2019.

The review "raises certain questions in relation to the project management process" around the cost blowout and delay, Turquoise Hill said.

"Rio Tinto will engage with the OT (Oyu Tolgoi) Board as soon as we have had the opportunity to review the report in detail," Australia's Rio Tinto said in an emailed statement.

Rio owns 51% of Turquoise Hill, which owns 66% of the Oyu Tolgoi mine. The rest of the mine is owned by the government of Mongolia.

Costs to expand the Oyu Tolgoi mine, Rio's biggest copper growth project, have ballooned up to $6.75 billion from its original budget of $5.3 billion in 2016, raising friction over funding with Turquoise Hill.

The Wall Street Journal was first to report the news https://www.wsj.com/articles/rio-tinto-mismanagement-caused-mongolia-copper-mines-woes-report-says-11628503201.

(Reporting by Priyanshi Mandhan in Bengaluru; Editing by Devika Syamnath and Subhranshu Sahu)

By Matt Earle

Matthew Earle is the Founder of MiningFeeds. In 2005, Matt founded MiningNerds.com to provide data and information to the mining investment community. This site was merged with Highgrade Review to form MiningFeeds. Matt has a B.Sc. degree with a minor in geology from the University of Toronto.

Comments are closed.

If you would like to receive our free newsletter via email, simply enter your email address below & click subscribe.

MOST ACTIVE MINING STOCKS

 Daily Gainers

 Belo Sun Mining Corp BSX.TO +70.59%
 Highbank Resources Ltd. HBK.V +50.00%
 Full Metal Minerals Ltd. FMM.V +42.86%
 AusQuest Ltd. AQD.AX +41.67%
 Casa Minerals Inc. CASA.V +30.00%
 CMC Metals Ltd. CMB.V +25.00%
 Belmont Resources Inc. BEA.V +25.00%
 New Stratus Energy Inc. NSE.V +22.22%
 Lincoln Mining Corp. LMG.V +22.22%
 Golden Arrow Resources Corp. GRG.V +18.18%